Future Projects

Chattey Rd. - Pleasant Run Rd. to Belt Line Rd. Improvements
Engineer: EJES, Inc.
Contractor: TBD
Project: Chattey Road is an existing two-lane asphalt roadway located within a residential community. The improved roadway will be a 27’ undivided concrete roadway with curb and gutter, closed drainage, sidewalks, retaining walls, sewer line crossings, water line replacement, landscaping and lighting.
Project Status: Design Phase at 95% completion. (9/16)
                             Appraisals are being completed for Right-of-Way Acquisition (10/16)
                             Appraisals are 20% Complete (11/16)
                             Appraisals are 60% Complete (12/16)

                             Appraisals are 90% Complete (1/17)
                             Right-of-Way Acquisition in progress (2/17)
                             Right-of-Way Acquisition in progress (3/17)
                             Right-of-Way Acquisition in progress (4/17)
                             Right-of-Way Acquisition in progress (5/17)
                             Right-of-Way Acquisition in progress (6/17)
                             Right-of-Way Acquisition 80% complete (7/17)
                             Right-of-Way Acquisition 90% complete (8/17)
                             Right-of-Way Acquisition 95% complete (9/17)
                             Right-of-Way Acquisition 95% complete (10/17)
Construction anticipated to begin Summer 2018
  
Pleasant Run Rd. - Joint MCIP Project # 1- Dallas County
Engineer: Garver
Contractor: TBD
• Project:  Pleasant Run Rd. (Westmoreland Rd. – Cockrell Hill Rd.), 2 lane concrete roadway w/curb and gutter and storm drain. 
Project Status: Pre-Design - Consultant to be selected fall 2016 (9/16)
                             Preparing RFQ for consultant selection (10/16)
                             RFQ advertised (11/16)
                             Waiting period after RFQ advertised (12/16)

                             SOQ's have been submitted for review (1/17)
                             Garver has been selected for contract negotiations for professional services contract (2/17)
                             Consultant contract negotiations ongoing (3/17)
                             Consultant contract negotiations ongoing (4/17)
                             Contract negotiations complete (5/17)
                             Design Contract awarded by City Council (6/17)
                             Consultant preparing to start surveying work (7/17)
                             Surveying work is 90% complete (8/17)
                             Surveying work complete (9/17)
                             Surveying work complete (10/17)
Construction anticipated to begin January 2019

Westmoreland Rd. - Joint MCIP Project # 2 - Dallas County
Engineer: Freese and Nichols
Contractor: TBD
• Project:  Westmoreland Rd. (Belt Line Rd. – Parkerville Rd.), 2 lane concrete roadway w/curb and gutter and storm drain. 
Project Status: Design (10/17)
Construction anticipated to begin Summer 2019
     
Whispering Oaks Drainage
* Engineer: Dallas County
* Contractor: TBD
* Project:
Protect city outfall structure from falling into the creek.
                 Design Phase (10/17)
Construction anticipated to begin January 2018
 

Fire Station #2 Relocation

Architect: Architect Design Group, Inc. (ADG) 
Contractor: TBD
Project: A new Fire Station With Fire Administration offices will be constructed in the vicinity of Parks Dr. and Belt Line Rd. Upon  completion of the new Fire Station, the existing Fire Station at Hampton Rd. and First St., will be removed.
Project Status: Design Phase 85% complete (9/16)
                             Design Phase 90% complete (10/16)
                             Design Phase 90% complete (11/16)
                             Design Phase 95% complete (12/16)

                             Design Phase complete, Preparing Bid Documents (1/17)
                             Project previously on hold from 2/17 - 5/17
                             Redesign requested and plans forthcoming to the City for review (5/17)
                             Redesign requested and plans forthcoming to the City for review (6/17)
                             Redesign requested and plans forthcoming to the City for review (7/17)
                             Redesign requested and plans forthcoming to the City for review (8/17)
                             Redesign requested and plans forthcoming to the City for review (9/17)
                             Redesign requested and plans forthcoming to the City for review (10/17)
• Construction anticipated to begin Summer 2018
 
Corner Theatre
Architect: PBK Architects, Inc. 
Contractor: 3i Contracting
Project: The corner Theater of Town Center will be reconstructed into a "Black Box," theatre concept. This renovation will allow a variety of users to lease this area for different events including: Theatre events, receptions, dinners, etc.
Project Status: Design Phase 90% complete (9/16)
                             Design Phase 100% complete Bidding slated to begin in December 2016 (11/16)
                             Bidding slated to begin in December (12/16)

                             Bids were received on 1/28, Construction Contract Scheduled for City Council Approval in  
                             March (1/17)
                             Demolition started (2/17)
                             Demolition completed (3/17)
                             Construction 50% complete (4/17)
                             Construction 75% complete (5/17)
                             Construction 95% complete (6/17)
                             Construction 98% complete (7/17)
                             Construction 99% complete (8/17)
                             Construction 99% complete (9/17)
                             Construction complete (10/17)
Construction commenced on March 13, 2017
• Project completion scheduled for November 2017