Future Projects

Chattey Rd. - Pleasant Run Rd. to Belt Line Rd. Improvements
Engineer: EJES, Inc.
Contractor: TBD
Project: Chattey Road is an existing two-lane asphalt roadway located within a residential community. The improved roadway will be a 27’ undivided concrete roadway with curb and gutter, closed drainage, sidewalks, retaining walls, sewer line crossings, water line replacement, landscaping and lighting.
Project Status: 
Right-of-Way Acquisition 80% complete (7/17)
                             Right-of-Way Acquisition 90% complete (8/17)
                             Right-of-Way Acquisition 95% complete (9/17)
                             Right-of-Way Acquisition 95% complete (10/17)
                             Right-of-Way Acquisition complete (11/17)
                              Franchise Utility Relocations Started (12/17)
Construction anticipated to begin Summer 2018
  
Pleasant Run Rd. - Joint MCIP Project # 1- Dallas County
Engineer: Garver
Contractor: TBD
• Project:  Pleasant Run Rd. (Westmoreland Rd. – Cockrell Hill Rd.), 2 lane concrete roadway w/curb and gutter and storm drain. 
Project Status: 
Consultant preparing to start surveying work (7/17)
                             Surveying work is 90% complete (8/17)
                             Surveying work complete (9/17)
                             Surveying work complete (10/17)
                             Alignment study underway to determine right-of-way acquisition needs (11/17)
                             Alignment study underway to determine right-of-way acquisition needs (12/17)
Construction anticipated to begin January 2019

Westmoreland Rd. - Joint MCIP Project # 2 - Dallas County
Engineer: Freese and Nichols
Contractor: TBD
• Project:  Westmoreland Rd. (Belt Line Rd. – Parkerville Rd.), 2 lane concrete roadway w/curb and gutter and storm drain. 
Project Status: Design (10/17)
                             Design contract awarded to Freese and Nichols, Inc. on November 21, 2017 (11/17)
                             Continuing Alignment Study (12/17)
Construction anticipated to begin Summer 2019
     
Whispering Oaks Drainage
* Engineer: Dallas County
* Contractor: TBD
* Project:
Protect city outfall structure from falling into the creek.
                 Design Phase (10/17)
                 Surveying underway (11/17)
                 Surveying anticipated to begin January 2018 (12/17)
Construction anticipated to begin January 2018
 

Fire Station #2 Relocation

Architect: Architect Design Group, Inc. (ADG) 
Contractor: TBD
Project: A new Fire Station With Fire Administration offices will be constructed in the vicinity of Parks Dr. and Belt Line Rd. Upon  completion of the new Fire Station, the existing Fire Station at Hampton Rd. and First St., will be removed.
Project Status: 
Redesign requested and plans forthcoming to the City for review (7/17)
                             Redesign requested and plans forthcoming to the City for review (8/17)
                             Redesign requested and plans forthcoming to the City for review (9/17)
                             Redesign requested and plans forthcoming to the City for review (10/17)
                             Redesign requested and plans forthcoming to the City for review (11/17)
                              Design Complete, Project expected to advertise in February 2018 (12/17)
• Construction anticipated to begin Summer 2018
  
2018 Water/Wastewater Renovation & Replacement Project - Phase 1
Hunters Creek Dr., Foxwood Dr., Prairie Creek Dr. and Shadywood Lane
• Engineer: Dick Perkins, P.E.
Contractor: TBD
Project: Included in the Capital improvement Program (CIP) is the annual expenditure of R & R
(Renovation and Replacement) funds which are used to upgrade deteriorating water and wastewater infrastructure. The current R & R Project includes various locations with varying degrees of deterioration of the existing clay tile sewer lines and cast iron water
lines. In most cases the infrastructure is 40-50 years old. The water and sewer main lines will be replaced with Polyvinyl Chloride (PVC) pipe. In addition, water service lines will be replaced (City side of the meters) and sewer lines will be replaced up to the
property lines with cleanouts being installed at the property line. In accordance with the CIP, the following streets have water,sewer and paving infrastructure that will be replaced:

Project Status: Design (12/17)

Projected Completion Fall 2018


2018 Repaving Project - Phase 2
Hunters Creek Dr., Foxwood Dr., Prairie Creek Dr. and Shadywood Lane
• Engineer: Dick Perkins, P.E.
Contractor: TBD
Project:Included in the Capital Improvement Program is the annual reconstruction of residential and collector asphalt streets. The scope of work for this project will consist of the pulverization of the existing asphalt, cement stabilization of the base material to a depth
of 6", and the construction of a new 6" asphalt roadway. 

Project Status: Design (12/17)

Projected Completion Fall 2018