Future Projects

Chattey Rd. - Pleasant Run Rd. to Belt Line Rd. Improvements
Engineer: EJES, Inc.
Contractor: TBD
Project: Chattey Road is an existing two-lane asphalt roadway located within a residential community. The improved roadway will be a 27’ undivided concrete roadway with curb and gutter, closed drainage, sidewalks, retaining walls, sewer line crossings, water line replacement, landscaping and lighting.
Project Status: 
Utility Relocations Complete (6/18)
                             Utility Relocations Complete (7/18)
                             Final Plans Complete (8/18)
                             Bidding Project for construction (9/18)
                             Project Awarded to Contractor (10/18)
                             Contractor Execution (11/18)
Construction anticipated to begin Winter 2019
   
Pleasant Run Rd. - Joint MCIP Project # 1- Dallas County
Engineer: Garver
Contractor: TBD
• Project:  Pleasant Run Rd. (Westmoreland Rd. – Cockrell Hill Rd.), 2 lane concrete roadway w/curb and gutter and storm drain. 
Project Status: 
Preliminary roadway profiles and cross section designs underway, as well utility alignment study (6/18)
                             Preliminary roadway profiles and cross section designs underway, as well utility alignment study (7/18)
                             Preliminary roadway profiles and cross section design ongoing (8/18)
                             Preliminary design ongoing (9/18)
                             Preliminary design ongoing (10/18)
                             Preliminary design ongoing (11/18)
Construction anticipated to begin Winter 2020
 

Westmoreland Rd. - Joint MCIP Project # 2 - Dallas County
Engineer: Freese and Nichols
Contractor: TBD
• Project:  Westmoreland Rd. (Belt Line Rd. – Parkerville Rd.), 2 lane concrete roadway w/curb and gutter and storm drain. 
Project Status: Preliminary surveying started (6/18)
                             Preliminary surveying ongoing (7/18)
                             Preliminary surveying ongoing (8/18)
                             Preliminary surveying ongoing (9/18)
                             Preliminary surveying ongoing (10/18)
                             Preliminary design (11/18)
Construction anticipated to begin Winter 2020
      
Whispering Oaks Drainage
* Engineer: Dallas County
* Contractor: TBD
* Project:
Protect city outfall structure from falling into the creek.
Project Status:  Final design  under review (6/18)
                              Final design  under review (7/18)
                              Final design  under review (8/18)
                              Final design  under review (9/18)
                              Final design  under review (10/18)
                              Final design  in progress (11/18)
Construction anticipated to begin Spring 2019
   

2018 Water/Wastewater Renovation & Replacement Project - Phase 1
Hunters Creek Dr., Foxwood Dr., Prairie Creek Dr. and Shadywood Lane
• Engineer: Dick Perkins, P.E.
Contractor: TBD
Project: Included in the Capital improvement Program (CIP) is the annual expenditure of R & R
(Renovation and Replacement) funds which are used to upgrade deteriorating water and wastewater infrastructure. The current R & R Project includes various locations with varying degrees of deterioration of the existing clay tile sewer lines and cast iron water
lines. In most cases the infrastructure is 40-50 years old. The water and sewer main lines will be replaced with Polyvinyl Chloride (PVC) pipe. In addition, water service lines will be replaced (City side of the meters) and sewer lines will be replaced up to the
property lines with cleanouts being installed at the property line. In accordance with the CIP, the following streets have water, sewer and paving infrastructure that will be replaced:

Project Status: 
Design (6/18)
                             Design (7/18)
                             Design Complete (8/18)
 
                            Advertise/Bid for Construction (9/18)
                             Project Awarded to Contractor (10/18)
                             Pipe bursting sanitary sewer lines on Hunters Creek (11/18)
• Construction anticipated to begin Fall 2018

2018 Repaving Project - Phase 2
Hunters Creek Dr., Foxwood Dr., Prairie Creek Dr. and Shadywood Lane
• Engineer: Dick Perkins, P.E.
Contractor: TBD
Project:Included in the Capital Improvement Program is the annual reconstruction of residential and collector asphalt streets. The scope of work for this project will consist of the pulverization of the existing asphalt, cement stabilization of the base material to a depth
of 6", and the construction of a new 6" asphalt roadway. 

Project Status: 
Design (6/18)
                             Design (7/18)
                             Design (8/18)
 
                            Initiating Advertising/bidding for construction (9/18)
                             Advertising/bidding for construction (10/18)
                             Evaluating bids (11/18)
Construction anticipated to begin Winter 2019